SJVN LIMITED
NATHPA JHAKRI HYDROELECTRIC POWER STATION

Total Power Generated Till Dated 20.06.10 is 38184.662 MU
Year 2010-2011 

DAILY GENERATION  REPORT FOR 20.06.10

GENERATION (MU) 

DAILY

MONTHLY Cuml.

YEARLY Cuml.

 

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

 

 

 

 

 

 

 

 

 

 

  

 

 

35.149

36.538

36.586

36.373

653.290

696.612

705.356

699.609

1882.128

2054.901

2071.873

2054.726

 

 

 

 

 

 

 

 

 

 

Unit No.

Daily (MU)

Running Hours 

Planned Outage

Forced Outage due to break down in M/C

Misc.

Availability 

Remarks

High    PPM/RED

ALERT

Less Avail. of Water

Grid Constraints ETC.

 

Gross

Ex-Bus

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Unit - 1 

6.271

6.237

24:00

0:00:00

0:00:00

0:00

0:00

0:00:00

24:00

Unit - 2 

6.172

6.148

24:00

0:00:00

0:00:00

0:00

0:00

0:00:00

24:00

Unit - 3 

5.762

5.723

24:00

0:00:00

0:00:00

0:00

0:00

0:00:00

24:00

Unit - 4 

6.203

6.180

24:00

0:00:00

0:00:00

0:00

0:00

0:00:00

24:00

Unit - 5 

5.966

5.910

24:00

0:00:00

0:00:00

0:00

0:00

0:00:00

24:00

Unit - 6 

6.212

6.175

24:00

0:00:00

0:00:00

0:00

0:00

0:00:00

24:00

 

Total

36.586

36.373

144:00

0:00:00

0:00:00

0:00

0:00

0:00:00

144:00

   

HYDROLOGICAL DATA

Discharge for Generation (Cumecs)
Satluj and Sholding 

Level (Meters)

SILT (PPM)

Inflow for Generation

639

Max. Dam Level

1495.35

 

Max.

at (Hr.Min)

Min.

at(Hr.Min)

Water Utilized

381

Min. Dam Level

1494.05

Wangtoo

2079

12:00

572

2:00

Water Spillage

-

Max. TRT Level

N/A

SFT

N/A

N/A

N/A

N/A

Water utilised for SFT flushing

-

Min. TRT Level

N/A

Draft Tube

2288

24:00

581

7:00

 

Coarse Silt Particles

-

Max.

Min.

Dam

0

0

Draft Tube

12