SJVN LIMITED
NATHPA JHAKRI HYDROELECTRIC POWER STATION

Total Power Generated Till Dated 18.02.10 is 35748.206 MU
Year 2009-2010 

DAILY GENERATION  REPORT FOR 18.02.10

GENERATION (MU) 

DAILY

MONTHLY Cuml.

YEARLY Cuml.

 

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

 

 

 

 

 

 

 

 

 

 

  

 

 

5.493

6.784

7.065

7.003

96.874

117.063

120.036

119.027

6214.636

6594.341

6650.928

6592.266

 

 

 

 

 

 

 

 

 

 

Unit No.

Daily (MU)

Running Hours 

Planned Outage

Forced Outage due to break down in M/C

Misc.

Availability 

Remarks

High    PPM/RED

ALERT

Less Avail. of Water

Grid Constraints ETC.

 

Gross

Ex-Bus

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

 U#3 is under Annaul maintenance w.e.f. 00:00 (12/02/10)

Unit - 1 

2.029

2.011

8:52

0:00:00

0:00:00

0:00

15:08

0:00:00

24:00

Unit - 2 

0.476

0.471

2:03

0:00:00

0:00:00

0:00

21:57

0:00:00

24:00

Unit - 3 

0.000

0.000

0:00

24:00:00

0:00:00

0:00

0:00

0:00:00

0:00

Unit - 4 

0.433

0.431

1:48

0:00:00

0:00:00

0:00

22:12

0:00:00

24:00

Unit - 5 

2.276

2.253

9:36

0:00:00

0:00:00

0:00

14:24

0:00:00

24:00

Unit - 6 

1.851

1.837

7:38

0:00:00

0:00:00

0:00

16:22

0:00:00

24:00

 

Total

7.065

7.003

29:57

24:00:00

0:00:00

0:00

90:03

0:00:00

120:00

   

HYDROLOGICAL DATA

Discharge for Generation (Cumecs)
Satluj and Sholding 

Level (Meters)

SILT (PPM)

Inflow for Generation

72

Max. Dam Level

1492.85

 

Max.

at (Hr.Min)

Min.

at(Hr.Min)

Water Utilized

74

Min. Dam Level

1476.75

Wangtoo

143

7:00

122

17:00

Water Spillage

-

Max. TRT Level

N/A

SFT

#REF!

#REF!

#REF!

#REF!

Water utilised for SFT flushing

-

Min. TRT Level

N/A

Draft Tube

57

22:00

45

20:00

 

Coarse Silt Particles

-

Max.

Min.

Dam

0

0

Draft Tube

0

0