Tipaimukh Multipurpose Hydro electric Project(1500 MW) is
located near Manipur Mizoram border, 500 m downstream of confluence of the
river Barak with Tuivai, in Churachandpur district of Manipur. The project
envisages construction of 162.80 metre high rock fill dam, with annual
estimated generation of 3,805.74 million units in a 90% dependable year with
an installed capacity of 6X250 MW, with firm power generation of 434.44 MW.
The project has been conceived as a multipurpose
storage project with the main objectives of hydropower development and flood
moderation at its downstream regime. Besides, the project will deliver a
large number of socio-economic benefits to the people living in & around the
project.
Present Status of Tipaimukh HE Project
1500 MW Tipaimukh HEP shall be implemented as a Joint
Venture with the equity participation of SJVN to the extent of 26%. Techno
Economic Clearance (TEC) of the project has accorded by CEA on dated July
02, 2003. The project also been cleared by Public Investment Board (PIB) on
dated January 31st , 2006. Environment Clearance (EC) has been
accorded by MOEF on October 10, 2008. Work for Forest Clearance is in
Progress.
Completion of Tipaimukh HE Project
The 1500 MW Tipaimukh HEP is expected to take 87 months
for completion and will come up during the 12th five year plan.
Project Cost
The completion cost of the project is estimated as Rs, 9211 Crores including IDC of Rs.
2643 crores at September, 2008 price level as per the FSR submitted to CEA.
Project Benefits
Besides the social and economic upliftment of the
people in its vicinity, the 1500 MW Tipaimukh Hydro Electric Project will
generate 3805.74 GWh of electrical energy in a 90 % dependable year.
|