| S.No. |
Description |
Date |
|
1. |
Approval of CEA for an installed capacity of 1020 MW at an estimated
cost of Rs.538.38 crores Project to be executed by HPSEB |
Feb, 1980 |
|
2. |
Environment Clearance |
June, 1980 |
|
3. |
Techno-economic clearance obtained from CEA for installed capacity of
1500 MW at an estimated cost of Rs.1649.17 crores at December, 1985 price level |
May, 1986 |
|
4. |
Forest Clearance |
July, 1986 |
|
5 |
PIB Approval |
Jan, 1988 |
|
6. |
Formation of SJVN |
May, 1988 |
|
7. |
CCEA approval for installed capacity of 1500 MW March, 1989 at an
estimated cost of Rs.1678.02 cores |
March, 1989 |
|
8. |
Approval of GOI for execution of NJHPP (6X250 MW) at an estimated cost
of Rs.1678.02 crores at September, 1988 price level by SJVN |
April, 1989 |
|
9. |
Approval of GOI obtained for receiving the World Bank Assistance of US$
437 million |
April, 1989 |
|
10. |
Signing of the World Bank Loan Agreement |
May, 1989 |
|
11. |
Effectiveness of the World Bank Loan |
Jan, 1990 |
|
12. |
Agreement between the Union Minister of State for Power and NES, GOI
and the Chief Minister, GOHP Signed |
July, 1991 |
|
13. |
Officially take over of NJHPP by SJVN |
Aug, 1991 |
|
14. |
Effective take over of NJHPP delayed due to agitation By HPSEB |
Feb., 1992 |
|
15. |
Approval by PIB for RCE-I |
April, 1993 |
|
16. |
Approval by CCEA for RCE-I |
June, 1993 |
|
17. |
Major Civil Works Contracts awarded |
June, 1993 |
|
18. |
Award of Contract for Generating Unit and Associated Equipments |
Nov, 1994 |
|
19. |
Submission of Revised Detailed Project Report incorporating Revised
Cost Estimate of Rs.7179.64 crores and Revised Commissioning Schedule of
all six units by March, 2002 to CEA. |
May, 1997 |
|
20. |
Approval of Revised Cost Estimates of Rs.7217.05 crores and Revised
Commissioning Schedule of all the units of NJHPP by March, 2002 by CEA |
Nov, 1997 |
|
21. |
Submission of application for re-categorization and extension of IBRD
Loan closing date to the World Bank |
Dec,1997 |
|
22. |
Re-categorization and extension of the IBRD Loan upto Dec.31, 1998 by
the World Bank |
Dec, 1997 |
|
23. |
Pre-PIB Memo for RCE-II submitted to MOP |
Jun, 1998 |
|
24. |
Pre-PIB Meeting held |
Jul, 1998 |
|
25. |
PIB Clearance for RCE-II of Rs 7666.31 crores |
Nov, 1998 |
|
26. |
CCEA Clearance for RCE-II of Rs 7666.31 crores |
May, 1999 |
|
27. |
Submission of RDPR - Nov.,2001 incorporating RCE-III of Rs.9083.34
crores at Sept.,2001 price level to MOP/CEA/Planning Commission |
Dec, 2001 |
|
28. |
CEA clearance for hard cost (Excluding Claims and Interest During
Construction etc.) of RCE-III of Rs.6218.29 crores |
Dec, 2002 |
|
29. |
Submission of Pre-PIB Memorandum incorporating RCE-III of Rs.8656.61*
crores at Sept.,2002 Price Level to MOP for approval.
(* The reimbursement of cost for providing Inter Connection Facility (ICF)
at Jhakri Switch Yard to M/s JHPL for Baspa Satge-II HE Project has been
finalised by Central Electricity Authority (CEA) at Rs. 62.86 crores and
has been ratified by the Board of Directors of SJVN, which is to be
deducted from the Capital Cost of the Project and about Rs.50 crores for
extension of cut and cover/Tunnel of Silt Flushing Tunnel is to be added) |
April, 2003 |
|
30. |
Ponding of Dam, Charging of Intake, Desilting Chamber no.4 and 27.4 km
long HRT and first run of Unit No.5 |
Aug 28, 2003 |
|
31. |
Synchronisation of Unit No.5 |
Sept 20, 2003 |
|
32. |
Commissioning (Commercial generation) of Unit No.5 |
Oct 06, 2003 |
|
33. |
Inauguration of first Unit of the Project (Unit # 5) |
Oct 14, 2003 |
|
34. |
Synchronisation of Unit No. 6 |
Nov 23, 2003 |
|
35. |
Commissioning (Commercial generation) of Unit No. 6 |
Jan 02, 2004 |
|
36. |
Synchronisation (Test Loaded) of Unit No. 4 |
Jan 22, 2004 |
|
37. |
Synchronisation (Test Loaded) of Unit No. 3 |
Feb 13, 2004 |
|
38. |
Synchronisation (Test Loaded) of Unit No. 2 |
Mar 09, 2004 |
|
39. |
Signing of MOU for the year 2004-05 between MOP, Govt. of India and
SJVN Ltd. |
Mar 29, 2004 |
|
40. |
Commissioning (Commercial generation) of Unit No.4 |
Mar 30, 2004 |
|
41. |
Synchronisation (Test Loaded) of Unit No. 1 |
Mar 31, 2004 |
|
42. |
Commissioning (Commercial generation) of Unit No. 3 |
Mar 31, 2004 |
|
43. |
Commissioning (Commercial Generation) of Unit No. 2 |
May 06, 2004 |
|
44. |
Commissioning (Commercial Generation) of Unit No. 1 |
May 18, 2004 |
|
43. |
SJVN gets ISO 9001:2000 Certification |
Feb 02, 2005 |
|
44. |
Dr. Manmohan Singh, Hon'ble PM of India dedicates NJHEP to the
Nation. |
May 28,2005 |