milestones
Milestones for the year 2011-12
 

Sr. No.

Description of  Milestone

Target date

Status upto 31.12.11

 1.

Diversion of forest land

31.12.11 GoHP recommended and forwarded the case to MOEF, GOI on 04.04.11, who directed Regional office Chandigarh for conducting site inspection. A presentation was made to MoEF's Regional Office, Chandigarh on 19.07.2011. Additional PCCF desired information on a detailed Performa relating to Diversion of Forest Land which was replied on 09.08.2011. Additional PCCF, Chandigarh inspected the site on 18th & 19 th Nov, 2011 and further forwarded the case to MOEF , GOI on 25.11.11.

2

Environment clearance from MoEF, Govt of India 15.12.11 Public Hearing was conducted at two places i) Nirath in Distt Shimla and ii) Khegsu in Distt Kullu on 05.05.2011 & 06.05.2011. Public Hearing at Parlog (Distt. Mandi ) on 07.05.2011 was adjourned after disruption by a group of locals, was rescheduled and conducted on 09.08.11. Himachal Pardesh State Pollution Control Board has forwarded the case to MOEF, GOI on 19.09.2011 for further action.The final copy of EIA/EMP report was submitted to MOEF, GOI on 31.10.2011. MOEF placed the case before Environmental Appraisal Committee(EAC). The EAC meeting date is awaited.

3

Award of work for 2 Bridges, 1 each at PH & Dam site 31.01.12 Estimates approved. NIT floated on 26.05.2011.Bid for Bridge at Dam site opened on 22.09.11 and for PH bridge on 31.10.11. Evaluation is in progress.
   