Sr. No. |
Description of Milestone |
Target date |
Status as on 31.12.11 |
|
1. |
Submission of Final DPR to CEA/MOE (RGoB) |
31.07.11 |
Final DPR submitted to CEA and RGoB on 30.06.11. Presentation has been made to CEA on 29.07.11.TEC awaited. Dam site road X-section field work has been completed. |
|
2. |
Submission of Baseline Demographic / Socio Economic Survey of the villagers in the affected area of Kholongchhu HEP |
31.07.10 |
Award made on 25.08.10. Final Report was submitted by the Consultant on 23.08.11. |
|
3 |
Submission of Final EIA/EMP Study Report |
31.12.11 |
The final report has been forwarded to RGoB on 31.10.11. The Comments/Approval from National Environment Commission, RGoB are awaited . |
|
4. |
Submission of application to RGoB for PEC |
30.09.11 |
The Forest deptt. accorded approval for carrying out topographical survey works on 23.06.09. Forest clearance for drilling and drifting obtained on 11.12.09 after necessary environmental clearance from Dzongkhag Administration. |