Memorandum of Understanding ( MOU ) has been signed with the Govt. of Nepal for
the execution of 900 MW Arun – III HE Project. Proposed to be located in the
Sankhuwasabha Distt. of Nepal which is 657 Km from Kathmandu via Birat Nagar.
The Survey license has been issued by Govt. of Nepal during July 2008 & has been further extended up to 16.01.2012. Survey License issued for 400 KV transmission line on 22.05.2009. TOR
clearance for IEE of roads issued by GoN on 20.04.2010.
Letter of intent issued on 23.05.2010 to carry out
infrastructure work at DAM & Power House site. Draft
implementation agreement submitted to GoN on 8th
June2010. FSR & commercial viability for 900 MW was
approved by CEA on 23.02.2010. Final DPR submitted to
CEA on 31.03.2011. Scoping document/ TOR resubmitted to Ministry of Environment, Nepal on 22.09.2011. DPR for Transmission Line submitted to CEA on 05.04.2011.
Survey License for Transmission extended upto 20.05.2012.
|